JULY 2013 an UPDATE
RECONSTRUCTION PLAN/ ACTUAL & PREVISIONNEL FINANCES - CONT
FIRST STAGE : MY HOUSE hard work + SUMMER KITCHEN = ALL DONE
Hard work HOUSE : DONE /
Estimated cost : 17500 TL / Actual cost : 16243 TL
SUmmer Kitchen ; DONE
estimated cost 500 TL / Actual cost : 200 TL
---------------------------------------------------------------------------------------------------------------
SECOND STAGE :
+ SOLAR ENERGY= DONE
+ FINISHING MY HOUSE = IN PROGRESS
+ FIXING DAMAGES = NOT STARTED
we will stay at the first step with only 2 solar panels of 180 W each with ONE GEL BATTERY and accessories (charge controler and inverter)
ACTUAL COST : 1350 TL = PAID AND INSTALLED
It is in fact NOT a priority at the moment to have a bigger solar system for watering only.
Watering is now provided by 5 simple and long hoses with cover the main gardens. Of course watering requires thus much longer time because it is all done by hand, but like this each tree is looked after individually which is also good
--> TO FINISH MY HOUSE is however the PRIORITY
because once my house is finished , i can move into it thus liberate the Saraswati tent in which i am living since the fire, thus YOGA PROGRAMs can resume in Saraswati tent.
TBA company is one company working on the Dam Construction, but not the one responsible for the fire. Its boss, seeing that my house would remain unfinished was wondering why, and sent a friend to ask me. And told me that he would be pleased to HELP ME by giving available material, machines which he has on the construction site.
Thanks to TBA i could thus receive one truck full of this "white earth" that is used for construction here.
And the "usta" - builder could already cover the walls with "mud plaster"
However temperatures being too high now, the work is suspended until some refreshing air comes ...
So
What has still to be done =
COVERING OF THE CEILING = Isolation, humidity protection, wood
COVERING THE FLOOR = Marble (free from Bucak- marble head quarter in Turkey!) on a lime/ sand base
COVERING BATHROOM = Tiles given by TBA
INSTALLING ELECTRIC CABLES AND WATER SYSTEM = hopefully material can be obtained from TBA
Planned cost : 3500 TL- 2000 TL PAID BY FRIENDS = 1500 TL
Details =
Material and transportation : Mud, lime, bulldozer, truck = FREE , given by TBA
Material to be paid : Isolation material glass wool + Wood for the ceiling = 1000 TL
Usta's team work : 2000 TL= PAID BY FRIENDS OF ANTALYA :o))))
Other little material: 500 TL
--> FIXING THE DAMAGES first step : SARASWATI and DURGA 'roofs = NOT STARTED
AIM : TO COVER BOTH ROOFS BEFORE WINTER because it is sure that they wont resist the next storms in winter
MATERIAL: sheet metal and wood
Why sheet metal ?
Because it show the best solidity in time, resistance to ALL adversities, fire, heat, rain, storms... and it is not too expensive
PLANNED COST 4000 TL
Details:
DURGA 220 m2 : material 2000 TL + work 1000 TL
SARASWATI 50 m2 : material 500 TL + work 500 TL
-------------------------------------------------------------------------------------------------------------
THIRD STAGE : FIXING THE LOTUS POND + BUILDING THE COMMON HOUSE
I was speaking of this stage in the previous article, but for the time being better to leave this in stand by and see what will be possible for this year.
Hopefully TBA will help for some hard work with Bull dozer to clean the devastated places ...
Lets see ..
Your good wishes and energies are more than WELCOME to help to continue !!
om shantii